HOW WE SET OUR TARIFFS

How we set our tariffs


All tariffs and charges in the FPS are governed by 3 key principles:

  • Set by a competitive process where appropriate and otherwise economically justified
  • Reflective of the nature of service being provided
  • Representative of a fair balance between risk taken and return earned


The Components of the Tariff


The tariff has been built up from 4 key components that fully reflect the cost of developing and operating the Forties System:

  • Historic Capital Investment
  • Future Operating Costs
  • Future Capital Costs
  • Future Decommissioning Costs


Historic Capital Investment


The magnitude of the Historic Capital Investment component has been evaluated following Office of Fair Trading guidance that states 'it is justifiable to seek recompense for a historic investment (through tariff) where it can be shown that the investor has not yet recovered a reasonable return on that investment.' Investment in FPS can be categorised into three individual investment phases (as shown in the diagram below). To fairly evaluate the return of the system each investment decision has been evaluated independently.

The £200m initial investment in the FPS in the 1970's was made primarily to export Forties Field oil production. As this investment was never expected to be recompensed by 3rd party tariff revenue it has been excluded from the historic capital investment component of the tariff.

The second £1bn investment phase in the early 1990's was made to expand the capacity of FPS in order to win additional 3rd party business. This investment was over and above that required to provide continued service to existing customers and did not have the security of guaranteed future volumes or revenue.

The profitability of the £1bn investment has been accessed by comparing the cost of capital of the project at the time of inception with the actual return achieved from business subsequently won (post '93).

A third tranche of investment was made in the mid 2010's to comply with environmental legislation to ensure future system longevity.  Further investment is anticipated for the first half of the 2020's to enable FPS to continue to provide services out to 2040 and beyond.

The analysis has shown that the return associated with the £1bn investment (including an equivalent notional return from INEOS equity business) has yet to meet the cost of capital. A return on the £400m investment is built into the standard tariff which is payable by new customers from 2014 onwards. In both cases the revenue required to meet the cost of capital has been assumed to be shared equally amongst all past and/or expected future barrels, as appropriate.

The ability to meet the cost of capital over the full life of the system may be inhibited by the ability to manage future risks such as:

  • Safety & Integrity
  • Environmental Legislation
  • Rising Costs
  • Reducing Throughputs
  • Decommissioning


These factors remain as significant risks for INEOS.

Future Operating and Capital Costs


INEOS will invest significant sums in FPS to maintain availability and integrity. The future operating and capital cost components have been estimated to evaluate the future cost of operating the system up to 2040 and then have been averaged across all forecast barrels.

Decommissioning Costs


In a similar manner, the total cost of decommissioning FPS System has been shared equally amongst all past and expected future barrels.

In the event that additional treatment is required (e.g. if fluids do not meet standard specification) the transportation tariff shall be amended accordingly to reflect the cost of providing such additional services.

INEOS's Operating Cost Option


The standard form FPS Transportation and Processing Agreement (TPA) contains an option for INEOS to switch customers from a tariff-based charge to a cost share based charge.

INEOS appreciates that FPS customers would like to understand if and when INEOS is likely to exercise this option.  The predominant factors which will influence INEOS's decision for onset of cost-share in FPS is long term system throughput, each entrant's utilisation of the FPS facilities and their current tarriff.  Clearly this will be dynamic, involving variables out-with INEOS direct control or inflluence.  Nevertheless we will be open and honest in our discussions with customers as to a range of likely dates for the onset of cost-share.