The countdown has started. Step by step, we are approaching our major maintenance shutdown TAR24. All our factory parts will be stopped for planned maintenance, inspections and cleaning. On September 16, work began on running down our three factories. On September 23, our production will be at a standstill and almost 250 external contractors will arrive and participate during the shutdown.

At our eastern gate, Verkstadsvägen, we have built a TAR Center for contractors and parking spaces. The gate is opened when necessary. The rotation gate is open around the clock. In this area, all reporting and permit management also takes place. See our estimated time management below. During the stop, there will be increased traffic in our immediate area as well as a risk of elevated noise levels in certain stages during the shutdown and start-up of the factories.

Facts TAR24 >>>

  • 2 Capex will be conducted.
  • At present, we have 1271 work orders in the system.
  • These works include 176 inspections.
  • That means 241 entries.

Time management >>>

V36-37: Run-down of the factories. The TAR Center is being built at Östra Porten. There are changing rooms, a dining room, an info center and here all work orders are written. Parking and all entry for contractors will take place in this area.

VCM V38: EDC area begins

CHLORINE V39-40: Stop 15 days

VCM V39-41: Stop 18 days

DS V39-40: Stop 12 days

PVC V39-40: Stop 12 days

9 October 18:00 The maintenance department returns the factory.

>>> Reminder - all contractors who will be taking part in TAR24 must complete our new entrance training - SSG Entrance INEOS Inovyn

Best regards // Project Leader TAR | Maintenance

 - A stop always means that we must keep extra high focus and work safely for the environment, each other and together!