Notice of unplanned restrictions:

Date Published Event Date Expected Duration of Outage Available Capacity in terms of Pipeline Throughput Comments
         

Notice of unplanned restrictions: 07 September 2020

 

 

             
Date Published

Event Date

Expected Duration of Outage Available Capacity in terms of Pipeline Throughput Comments        
08 September

08Sep 2020

From Monday 07 Sep 11:15 to Tuesday 08Sep 3:30 Unrestricted restriction removed at 3:30 am        
07 September 2020 07Sep 2020 From Monday 07 Sep 11:15 to tbc TBA GAEL Users only: Managing High GOR issue at Unity due to slower than anticipated

production returns.

       
07 September 2020 07 Sep 2020 From Monday 07 Sep 01:15 to 8:30 Unrestricted restriction removed at 8:30 am        
07 September 2020 07 Sep 2020 From Monday 07 Sep 01:15 to 9:30 190 mbd Imbalanced gas quantities within FPS requiring a managed throughput limit of 190 mbd to manage gas flaring.        

Notice of unplanned restrictions: 24 October 2019

Date Published

Event Date

Expected Duration of Outage Available Capacity in terms of Pipeline Throughput Comments
24 October 2019 24 October 2019 From Thursday 24th October 13:00 to 23:00 Unrestricted Operational issue resolved.
24 October 2019 24 October 2019 From Thursday 24th October 13:00 to 17:00 None Shutdown of FPS pipeline system due to loss of grid power

Notice of unplanned restrictions : 14 August 2019

Date Published Event Date Expected Duration of Outage Available Capacity in terms of Pipeline Throughput (bbls/d) Comments
27 August 2019 14 August 2019

From 27 August to 5 September

240,000 bbls

Delay to Train 3 restart due to integrity and operational issues.

21 August 2019 14 August 2019

1. From: Tuesday 20th August 7pm to Thursday 22nd August 7pm

2. From: Thursday 22nd August 7pm to Friday 23rd August 7pm

3. From: Friday 23rd August 7pm until repair is complete (anticipated 27th August)

1. 230,000 bbls

2. 200,000 bbls

3. 265,000 bbls

Delay to Train 3 restart due to emerging integrity issues and operational issues associated with 3rd party NGL infastructure.

17 August 2019 14 August 2019 From: 10:00 14/08/19 to 16:15 20/08/19 265,000 bbls

Delay to Train 3 restart due to emerging integrity issues and operational issues associated with 3rd party NGL infastructure.

16 August 2019 14 August 2019 From: 10:00 14/08/19 to 18:00 19/08/19 210,000 bbls

Delay to Train 3 restart due to emerging integrity issues and operational issues associated with 3rd party NGL infastructure.

15 August 2019 14 August 2019 From: 10:00 14/08/19 to 18:00 16/08/19 210,000 bbls

Delay to Train 3 restart due to emerging integrity issues.

14 August 2019 14 August 2019 From: 10:00 14/08/19 to 10:00 15/08/19 250000 bbls

Delay to Train 3 restart due to emerging integrity issues.

 

Update : Forties Charlie ESDV closure tests deferred (8th August)

The one day shutdown of Forties Charlie for ESDV tests will now take place on Friday 16th August, and not Friday 9th August as previously advised.

Impact : Shutdown for Forties Users. 24 hours. Availability capacity of pipeline throughput reduced by 100,000 bbls.


Update : Notice of Unplanned Outage 7th July 2019

Date Information Published Event Date Expected Duration of Outage Available Capacity in terms of Pipeline Throughput Comments
11 July 2019 07 July 2019 From: 12:33 07 July 2019 to 15:25 11 July 2019 Unrestricted

Operational issue resolved.

11 July 2019 07 July 2019 From: 12:33 07 July 2019 to 23:59 11 July 2019 190000 bbls

Unplanned outage affecting availability of capacity for FPS throughput.  Operational issue concerning main heater on Train 3 at Kinneil.

09 July 2019 07 July 2019 From: 12:33 07 July 2019 to 12:00 12 July 2019 190000 bbls

Unplanned outage affecting availability of capacity for FPS throughput.  Operational issue concerning main heater on Train 3 at Kinneil.

08 July 2019 07 July 2019 From: 12:33 07/07/19 to 23:59 10/07/19 190000 bbls

Unplanned outage affecting availability of capacity for FPS throughput.  Operational issue concerning main heater on Train 3 at Kinneil.

07 July 2019 07 July 2019 From: 12:00 07/07/19 to 12:00 09/07/19 150000 bbls

Unplanned outage affecting availability of capacity for FPS throughput.  Operational issue concerning main heater on Train 3 at Kinneil.

 

Further update to follow during 08/07/19.